Glas facade closed
Thursday, 23. March 2023 | SAP Garden: Glas facade closed
Glas facade closed// NEWSOur glass façade was closed in mid-March. This marks the completion of another construction phase by FRENER & REIFER. The glass outer wall encloses the ground floor as well as level 1 and level 2.
The numbers:
716 cells with a total area of 4,938 m².
Production of the cells from 11/2021 - 07/2022 in the South Tyrolean factory. A separate production line had to be set up for this.
Assembly at the construction site in the Olympiapark München from 11/2022 - 03/2023.
On average, 8 fitters were working on the cell assembly.
Weiterer Baufortschritt: Glasfassade geschlossen!
// AKTUELLES
1/4
2/4
3/4
4/4
Production of the exterior facade// NEWS
Site Tour for Hainer, Hoeneß and Pesic// NEWS
Mit Video
Red Bulls Schütz and Fießinger go head to head on the construction site// NEWS
Production of the exterior facade// NEWS
Site Tour for Hainer, Hoeneß and Pesic// NEWS
Mit Video
Red Bulls Schütz and Fießinger go head to head on the construction site// NEWS
SAP